Al Khoud Residential Villa

Records

Everything that happened, everything that was asked, and every decision behind it.

Every discussion is attached to a record — there is no project-wide thread.

Honeycombing at column head C4

ActivitySTR-430 FF Slab Concrete Pour

Open
  1. C

    Surface honeycombing identified at column head C4 during the post-pour walk. Please propose a method for making good before this pour is certified.

    Eng. Yousuf Al Rawahi · 20 Feb 2027, 13:20

  2. C

    Method statement uploaded. We propose breaking out to sound concrete and reinstating with a flowable repair mortar, then a bonding coat.

    Salim Al Hinai · 21 Feb 2027, 08:051

Which approved option suits the villa finish?

MaterialMAT-005 Porcelain Floor Tiles

Open
  1. C

    Is the difference between the three options only price, or is there a quality difference I should know about?

    Ahmed Al Balushi · 19 Feb 2027, 10:00

  2. C

    All three meet the specification. The RAK option is approved with a comment — its slip certificate covers the matt finish only, so wet areas must use matt. The Porcelanosa option has the shortest lead time.

    Eng. Yousuf Al Rawahi · 21 Feb 2027, 16:40

Access arrangements for the 26 Feb visit

InspectionINS-015 FF Slab post-pour inspection

Open
  1. C

    Scaffold access to the slab edge will be available from 07:00. Please ask the inspector to report to the site office first.

    Salim Al Hinai · 21 Feb 2027, 07:30

  2. C

    Noted. We will attend at 10:30 as scheduled.

    Eng. Yousuf Al Rawahi · 21 Feb 2027, 09:12