Records
Everything that happened, everything that was asked, and every decision behind it.
21 Feb 2027
- 11:05INS-016 requested for staircase core lift 3.Salim Al Hinai · 21 Feb 2027, 11:05
- 08:05Comment on STR-430 FF Slab Concrete Pour: honeycombing at column head C4.Salim Al Hinai · 21 Feb 2027, 08:05
- 05:506 photographs uploaded against STR-440 first floor slab curing.Salim Al Hinai · 21 Feb 2027, 05:50
- 05:40Progress reported on STR-440 FF Slab Curing at 55%.Salim Al Hinai · 21 Feb 2027, 05:40
20 Feb 2027
- 09:00Aluminium windows — three supplier submissions lodged for technical review.Salim Al Hinai · 20 Feb 2027, 09:00
18 Feb 2027
- 11:40RFI-046 raised to the contractor: updated structural calculation for the first floor slab.Eng. Yousuf Al Rawahi · 18 Feb 2027, 11:40
17 Feb 2027
- 14:00INS-014 approved with comments. Pour to grid 1–6 authorised.Eng. Yousuf Al Rawahi · 17 Feb 2027, 14:00
- 06:30Schedule Rev 03 submitted — revised structural sequence, +6 days completion impact.Project Planner · 17 Feb 2027, 06:30
11 Feb 2027
- 09:30IPC-002 issued at 82.2% against a 91.3% claim. Net OMR 49,743.330 awaiting client approval.Eng. Yousuf Al Rawahi · 11 Feb 2027, 09:30
- 09:20Stage 02 certified at 82.2% with three outstanding items retained.Eng. Yousuf Al Rawahi · 11 Feb 2027, 09:20
10 Feb 2027
- 08:30ISS-021 raised against consultant: late structural shop drawing approval, +5 days estimated.Salim Al Hinai · 10 Feb 2027, 08:30
05 Feb 2027
- 06:45Stage 02 payment request PR-2027-002 submitted claiming 91.3%.Salim Al Hinai · 05 Feb 2027, 06:45
04 Feb 2027
- 07:30Stage 02 Substructure completion requested at 91.3% reported.Salim Al Hinai · 04 Feb 2027, 07:30
29 Jan 2027
- 15:30Porcelain floor tiles — three supplier options approved for client selection.Eng. Yousuf Al Rawahi · 29 Jan 2027, 15:30
16 Jan 2027
- 12:30INS-012 rejected — compaction certificates and north-face tanking outstanding.Eng. Yousuf Al Rawahi · 16 Jan 2027, 12:30
- 12:10DR-012 raised to the contractor: compaction test certificates for the north elevation.Eng. Yousuf Al Rawahi · 16 Jan 2027, 12:10
- 12:00ISS-019 raised against contractor: compaction test certificates not provided.Eng. Yousuf Al Rawahi · 16 Jan 2027, 12:00
08 Jan 2027
- 06:207 photographs uploaded against SUB-160 foundation waterproofing.Salim Al Hinai · 08 Jan 2027, 06:20
22 Dec 2026
- 08:00Concrete cube test results uploaded for the ground slab pour.Salim Al Hinai · 22 Dec 2026, 08:00
12 Dec 2026
- 13:00INS-009 ground slab pre-pour inspection approved. Pour authorised.Eng. Yousuf Al Rawahi · 12 Dec 2026, 13:00
04 Dec 2026
- 14:05Schedule Rev 02 approved with condition on flood testing sequence.Eng. Yousuf Al Rawahi · 04 Dec 2026, 14:05
02 Nov 2026
- 14:20Foundation waterproofing membrane approved with comments — protection board within 48 hours.Eng. Yousuf Al Rawahi · 02 Nov 2026, 14:20
29 Oct 2026
- 09:00Payment PAY-2026-001 recorded against IPC-001.Ahmed Al Balushi · 29 Oct 2026, 09:00
25 Oct 2026
- 08:00Stage 01 payment approved.Ahmed Al Balushi · 25 Oct 2026, 08:00
24 Oct 2026
- 09:15Stage 01 Preliminaries & Site Setup approved by the client.Ahmed Al Balushi · 24 Oct 2026, 09:15
22 Oct 2026
- 10:15IPC-001 issued. Certified OMR 12,250.000 gross, net OMR 11,637.500.Eng. Yousuf Al Rawahi · 22 Oct 2026, 10:15
20 Oct 2026
- 10:00Stage 01 certified at 100% by Eng. Yousuf Al Rawahi.Eng. Yousuf Al Rawahi · 20 Oct 2026, 10:00
18 Oct 2026
- 07:20Stage 01 payment request PR-2026-001 submitted for OMR 12,250.000.Salim Al Hinai · 18 Oct 2026, 07:20
16 Oct 2026
- 09:45Ready-mix concrete C40/20 approved. Trial cube results accepted.Eng. Yousuf Al Rawahi · 16 Oct 2026, 09:45
- 07:10Stage 01 Preliminaries & Site Setup completion requested at 100% verified.Salim Al Hinai · 16 Oct 2026, 07:10
02 Oct 2026
- 11:00Reinforcement steel approved. Mill certificates accepted.Eng. Yousuf Al Rawahi · 02 Oct 2026, 11:00
28 Sep 2026
- 08:30Reinforcement steel submitted — Qatar Steel B500B.Salim Al Hinai · 28 Sep 2026, 08:30
15 Sep 2026
- 07:00Project activated. Primavera no longer required for day-to-day operation.eBinaa · 15 Sep 2026, 07:00
10 Sep 2026
- 09:24Primavera baseline AlKhoud_Villa_Baseline_R0.xer imported and saved as Baseline R0.Eng. Yousuf Al Rawahi · 10 Sep 2026, 09:24
02 Sep 2026
- 11:00Contract CON-2026-0184 signed by all three parties; project created.eBinaa · 02 Sep 2026, 11:00