Compaction test certificates — north elevation
OverdueDR-012: Provide independent compaction test results for the backfill placed to the north elevation.
- From
- Consultant
Data date 22 Feb 2027 · Forecast completion 21 Nov 2027
13 days late
finishing 21 Nov 2027
Stage 3 of 11·Ground Floor Structure
5 activities on site today
FF Slab Concrete Pour
78% of 100%
Blocked by an open issue
FF Column Reinforcement
10% of 30%
DR-012: Provide independent compaction test results for the backfill placed to the north elevation.
RFI-046: Provide the revised structural calculation supporting the coupler arrangement at gridline 9 following the change issued under S-204 Rev C.
DR-014: Submit the manufacturer product certificate and current test report for the foundation tanking membrane applied to the south and east elevations.
Reported done, but only 96% is checked. Nothing gets paid until it is.
10 need your action · 5 with others
DR-012: Provide independent compaction test results for the backfill placed to the north elevation.
On the critical path and behind today's target.
Should have finished by now, and it is on the critical path.
RFI-046: Provide the revised structural calculation supporting the coupler arrangement at gridline 9 following the change issued under S-204 Rev C.
DR-014: Submit the manufacturer product certificate and current test report for the foundation tanking membrane applied to the south and east elevations.
Reported done, but only 96% is checked. Nothing gets paid until it is.
Reported done, but only 95% is checked. Nothing gets paid until it is.
RFI-047 — no reply yet.
CR-008 — no reply yet.
Waiting for the consultant to review it.
Should have finished by now, and it is on the critical path.
Blocked by: Late structural shop drawing approval
Should have finished by now, and it is on the critical path.
Blocked by: Late structural shop drawing approval
On the critical path and behind today's target.
Blocked by: Late structural shop drawing approval
1 more due later — nothing needed today.
Why it’s late: Late structural shop drawing approval
12 key jobs behind · 2 open issues
See what’s holding it upProgress, stages, money and contract
As at 22 Feb 2027
Measured by contract value: OMR 90,450 of OMR 245,000 of work is confirmed done on site.
Next milestone: Ground Floor Structure Complete·expected 17 Mar 2027
Payment stages, driven by checked progress
Stage 01·Preliminaries & Site Setup
OMR 12,250 · 5% of contract · 5 activities
Stage 02·Substructure
OMR 63,700 · 26% of contract · 15 activities
Stage 03·Ground Floor Structure
OMR 31,500 · 12.86% of contract · 11 activities
Stage 04·First Floor Structure
OMR 26,950 · 11% of contract · 10 activities
Stage 05·Roofing & Blockwork
OMR 22,050 · 9% of contract · 9 activities
Stage 06·MEP First Fix
OMR 17,150 · 7% of contract · 8 activities
Stage 07·Waterproofing & Plastering
OMR 14,700 · 6% of contract · 6 activities
Stage 08·Tiling, Doors & Windows
OMR 19,600 · 8% of contract · 6 activities
Stage 09·MEP Second Fix & Painting
OMR 17,150 · 7% of contract · 7 activities
Stage 10·External Works
OMR 12,250 · 5% of contract · 5 activities
Stage 11·Testing, Commissioning & Handover
OMR 7,700 · 3.14% of contract · 7 activities
Client
Ahmed Al Balushi
Ahmed Al Balushi · Owner / Employer
Contractor
Al Noor Construction LLC
Salim Al Hinai · Main Contractor
CR 1148296
Consultant
Modern Engineering Consultancy
Eng. Yousuf Al Rawahi · Supervising Consultant
CR 1092447 / OSE-C-2214