Al Khoud Residential Villa

Reports

Progress, commercial position and the audit trail — the three questions every construction project is asked.

Reporting as at data date 22 Feb 2027

Progress report

Planned against reported and verified, by contract stage.

Planned43.3%
Contractor reported40.1%
Consultant verified36.9%
Variance to plan-6.4%Forecast +13 days
StageNameProgressPlannedReportedVerifiedVarianceValue verified
Stage 01Preliminaries & Site Setup100%100%100%0%OMR 12,250
Stage 02Substructure100%91%82%-18%OMR 52,361
Stage 03Ground Floor Structure93%86%81%-12%OMR 25,515
Stage 04First Floor Structure4%2%1%-2%OMR 323
Stage 05Roofing & Blockwork0%0%0%0%OMR 0
Stage 06MEP First Fix0%0%0%0%OMR 0
Stage 07Waterproofing & Plastering0%0%0%0%OMR 0
Stage 08Tiling, Doors & Windows0%0%0%0%OMR 0
Stage 09MEP Second Fix & Painting0%0%0%0%OMR 0
Stage 10External Works0%0%0%0%OMR 0
Stage 11Testing, Commissioning & Handover0%0%0%0%OMR 0
Planned
From the baseline schedule. Where the contract says the work should be.
Contractor reported
What the contractor claims is complete. A claim — never a basis for payment.
Consultant verified
What a named consultant certified on site. The only value that drives money.

Commercial report

Certified, retained and paid against the contract sum.

Contract valueOMR 245,000
Verified work valueOMR 90,45036.9% of contract
Balance to completeOMR 154,550
Certified to dateOMR 64,611
Retention heldOMR 3,2315% of certified
Outstanding to contractorOMR 49,743

Verified work value (OMR 90,450) exceeds certified value (OMR 64,611) because work verified since the last certificate has not yet been claimed. That difference is the contractor’s next application.

Audit trail

Every state change on this project, most recent first.

35 events
  1. INS-016 requested for staircase core lift 3.

    Salim Al Hinai·21 Feb 2027, 11:05

  2. Comment on STR-430 FF Slab Concrete Pour: honeycombing at column head C4.

    Salim Al Hinai·21 Feb 2027, 08:05

  3. 6 photographs uploaded against STR-440 first floor slab curing.

    Salim Al Hinai·21 Feb 2027, 05:50

  4. Progress reported on STR-440 FF Slab Curing at 55%.

    Salim Al Hinai·21 Feb 2027, 05:40

  5. Aluminium windows — three supplier submissions lodged for technical review.

    Salim Al Hinai·20 Feb 2027, 09:00

  6. RFI-046 raised to the contractor: updated structural calculation for the first floor slab.

    Eng. Yousuf Al Rawahi·18 Feb 2027, 11:40

  7. INS-014 approved with comments. Pour to grid 1–6 authorised.

    Eng. Yousuf Al Rawahi·17 Feb 2027, 14:00

  8. Schedule Rev 03 submitted — revised structural sequence, +6 days completion impact.

    Project Planner·17 Feb 2027, 06:30

  9. IPC-002 issued at 82.2% against a 91.3% claim. Net OMR 49,743.330 awaiting client approval.

    Eng. Yousuf Al Rawahi·11 Feb 2027, 09:30

  10. Stage 02 certified at 82.2% with three outstanding items retained.

    Eng. Yousuf Al Rawahi·11 Feb 2027, 09:20

  11. ISS-021 raised against consultant: late structural shop drawing approval, +5 days estimated.

    Salim Al Hinai·10 Feb 2027, 08:30

  12. Stage 02 payment request PR-2027-002 submitted claiming 91.3%.

    Salim Al Hinai·05 Feb 2027, 06:45

  13. Stage 02 Substructure completion requested at 91.3% reported.

    Salim Al Hinai·04 Feb 2027, 07:30

  14. Porcelain floor tiles — three supplier options approved for client selection.

    Eng. Yousuf Al Rawahi·29 Jan 2027, 15:30

  15. INS-012 rejected — compaction certificates and north-face tanking outstanding.

    Eng. Yousuf Al Rawahi·16 Jan 2027, 12:30

  16. DR-012 raised to the contractor: compaction test certificates for the north elevation.

    Eng. Yousuf Al Rawahi·16 Jan 2027, 12:10

  17. ISS-019 raised against contractor: compaction test certificates not provided.

    Eng. Yousuf Al Rawahi·16 Jan 2027, 12:00

  18. 7 photographs uploaded against SUB-160 foundation waterproofing.

    Salim Al Hinai·08 Jan 2027, 06:20

  19. Concrete cube test results uploaded for the ground slab pour.

    Salim Al Hinai·22 Dec 2026, 08:00

  20. INS-009 ground slab pre-pour inspection approved. Pour authorised.

    Eng. Yousuf Al Rawahi·12 Dec 2026, 13:00

  21. Schedule Rev 02 approved with condition on flood testing sequence.

    Eng. Yousuf Al Rawahi·04 Dec 2026, 14:05

  22. Foundation waterproofing membrane approved with comments — protection board within 48 hours.

    Eng. Yousuf Al Rawahi·02 Nov 2026, 14:20

  23. Payment PAY-2026-001 recorded against IPC-001.

    Ahmed Al Balushi·29 Oct 2026, 09:00

  24. Stage 01 payment approved.

    Ahmed Al Balushi·25 Oct 2026, 08:00

  25. Stage 01 Preliminaries & Site Setup approved by the client.

    Ahmed Al Balushi·24 Oct 2026, 09:15

  26. IPC-001 issued. Certified OMR 12,250.000 gross, net OMR 11,637.500.

    Eng. Yousuf Al Rawahi·22 Oct 2026, 10:15

  27. Stage 01 certified at 100% by Eng. Yousuf Al Rawahi.

    Eng. Yousuf Al Rawahi·20 Oct 2026, 10:00

  28. Stage 01 payment request PR-2026-001 submitted for OMR 12,250.000.

    Salim Al Hinai·18 Oct 2026, 07:20

  29. Ready-mix concrete C40/20 approved. Trial cube results accepted.

    Eng. Yousuf Al Rawahi·16 Oct 2026, 09:45

  30. Stage 01 Preliminaries & Site Setup completion requested at 100% verified.

    Salim Al Hinai·16 Oct 2026, 07:10

  31. Reinforcement steel approved. Mill certificates accepted.

    Eng. Yousuf Al Rawahi·02 Oct 2026, 11:00

  32. Reinforcement steel submitted — Qatar Steel B500B.

    Salim Al Hinai·28 Sep 2026, 08:30

  33. Project activated. Primavera no longer required for day-to-day operation.

    eBinaa·15 Sep 2026, 07:00

  34. Primavera baseline AlKhoud_Villa_Baseline_R0.xer imported and saved as Baseline R0.

    Eng. Yousuf Al Rawahi·10 Sep 2026, 09:24

  35. Contract CON-2026-0184 signed by all three parties; project created.

    eBinaa·02 Sep 2026, 11:00

Prototype note — Reports are rendered on screen only. Export to PDF and Excel, scheduled distribution, and the S-curve / earned-value chart set are not implemented — but every figure here is derived from the same selectors the screens use, so an export layer reads one source.