Payments
Certified value, retention and the commercial position. eBinaa records payments; it never moves money.
Commercial summary
PR-2026-001·Stage 01 Preliminaries & Site Setup
Submitted 18 Oct 2026 by Salim Al Hinai
Claim against certificate
- Contractor claimedat 100.0% reported
- OMR 12,250.000
- Consultant certified grossat 100.0% verified
- OMR 12,250.000
- Less retention (5%)
- − OMR 612.500
- Less previously certified
- − OMR 0.000
- Net certified
- OMR 11,637.500
Certification and approval chain
Contractor submitted
Salim Al Hinai · 18 Oct 2026
Consultant certified
Eng. Yousuf Al Rawahi · IPC-001 · 22 Oct 2026
Client approved
Ahmed Al Balushi · 25 Oct 2026
Payment recorded
OMR 11,637.500 · 29 Oct 2026
Eng. Yousuf Al Rawahi: Stage 01 works verified complete. Certified in full.
No action available to the contractor on this request.
PR-2027-002·Stage 02 Substructure
Submitted 05 Feb 2027 by Salim Al Hinai
Claim against certificate
- Contractor claimedat 91.3% reported
- OMR 58,158.100
- Consultant certified grossat 82.2% verified
- OMR 52,361.400
- Less retention (5%)
- − OMR 2,618.070
- Less previously certified
- − OMR 0.000
- Net certified
- OMR 49,743.330
OMR 5,796.700 not certified. The consultant reduced the claim to the progress actually verified on site.
Certification and approval chain
Contractor submitted
Salim Al Hinai · 05 Feb 2027
Consultant certified
Eng. Yousuf Al Rawahi · IPC-002 · 11 Feb 2027
Client approved
Pending
Payment recorded
Pending
Eng. Yousuf Al Rawahi: Certified at 82.2% against a claim of 91.3%. Foundation tanking to the north face and backfill compaction evidence remain outstanding and are excluded from this certificate.
No action available to the contractor on this request.
Stages not yet claimed
A payment request can only be raised once verified progress meets the stage threshold.
- Stage 03Ground Floor StructureOMR 31,50081.0% verified
- Stage 04First Floor StructureOMR 26,9501.2% verified
- Stage 05Roofing & BlockworkOMR 22,0500.0% verified
- Stage 06MEP First FixOMR 17,1500.0% verified
- Stage 07Waterproofing & PlasteringOMR 14,7000.0% verified
- Stage 08Tiling, Doors & WindowsOMR 19,6000.0% verified
- Stage 09MEP Second Fix & PaintingOMR 17,1500.0% verified
- Stage 10External WorksOMR 12,2500.0% verified
- Stage 11Testing, Commissioning & HandoverOMR 7,7000.0% verified
Prototype note — No money moves. Payment execution in the real platform runs through the existing contractor-service payment providers and the Finance service; this prototype records a payment against a certificate and stops there. Retention is accrued but release in moieties is not modelled.