Al Khoud Residential Villa

Payments

Certified value, retention and the commercial position. eBinaa records payments; it never moves money.

2 requests2 certificatesAwaiting client approval

Commercial summary

Contract valueOMR 245,000
Verified work valueOMR 90,450At verified progress
CertifiedOMR 64,611
PaidOMR 11,638
Retention heldOMR 3,2315% of certified
OutstandingOMR 49,743Certified, net, unpaid

PR-2026-001·Stage 01 Preliminaries & Site Setup

Submitted 18 Oct 2026 by Salim Al Hinai

Paid

Claim against certificate

Contractor claimedat 100.0% reported
OMR 12,250.000
Consultant certified grossat 100.0% verified
OMR 12,250.000
Less retention (5%)
− OMR 612.500
Less previously certified
− OMR 0.000
Net certified
OMR 11,637.500

Certification and approval chain

  1. Contractor submitted

    Salim Al Hinai · 18 Oct 2026

  2. Consultant certified

    Eng. Yousuf Al Rawahi · IPC-001 · 22 Oct 2026

  3. Client approved

    Ahmed Al Balushi · 25 Oct 2026

  4. Payment recorded

    OMR 11,637.500 · 29 Oct 2026

Eng. Yousuf Al Rawahi: Stage 01 works verified complete. Certified in full.

No action available to the contractor on this request.

PR-2027-002·Stage 02 Substructure

Submitted 05 Feb 2027 by Salim Al Hinai

Consultant Certified

Claim against certificate

Contractor claimedat 91.3% reported
OMR 58,158.100
Consultant certified grossat 82.2% verified
OMR 52,361.400
Less retention (5%)
− OMR 2,618.070
Less previously certified
− OMR 0.000
Net certified
OMR 49,743.330

OMR 5,796.700 not certified. The consultant reduced the claim to the progress actually verified on site.

Certification and approval chain

  1. Contractor submitted

    Salim Al Hinai · 05 Feb 2027

  2. Consultant certified

    Eng. Yousuf Al Rawahi · IPC-002 · 11 Feb 2027

  3. Client approved

    Pending

  4. Payment recorded

    Pending

Eng. Yousuf Al Rawahi: Certified at 82.2% against a claim of 91.3%. Foundation tanking to the north face and backfill compaction evidence remain outstanding and are excluded from this certificate.

No action available to the contractor on this request.

Stages not yet claimed

A payment request can only be raised once verified progress meets the stage threshold.

  • Stage 03Ground Floor StructureOMR 31,50081.0% verified
  • Stage 04First Floor StructureOMR 26,9501.2% verified
  • Stage 05Roofing & BlockworkOMR 22,0500.0% verified
  • Stage 06MEP First FixOMR 17,1500.0% verified
  • Stage 07Waterproofing & PlasteringOMR 14,7000.0% verified
  • Stage 08Tiling, Doors & WindowsOMR 19,6000.0% verified
  • Stage 09MEP Second Fix & PaintingOMR 17,1500.0% verified
  • Stage 10External WorksOMR 12,2500.0% verified
  • Stage 11Testing, Commissioning & HandoverOMR 7,7000.0% verified

Prototype note — No money moves. Payment execution in the real platform runs through the existing contractor-service payment providers and the Finance service; this prototype records a payment against a certificate and stops there. Retention is accrued but release in moieties is not modelled.