Payments
Certified value, retention and the commercial position. eBinaa records payments; it never moves money.
This month's claim
Verified work and material on site — not the whole stage
OMR 16,285 of reported work is not yet verified. Book the consultant — it carries to next month otherwise.
| Stage | Verified | Already certified | Earned | Claim |
|---|---|---|---|---|
| Ground Floor Structure | 81.0% | OMR 0.000 | OMR 54,148.500 | OMR 54,148.500 |
| First Floor Structure | 1.2% | OMR 0.000 | OMR 686.400 | OMR 686.400 |
Material on site, not yet built in
- Ready-Mix Concrete C40/2075.0% of OMR 18,600.000OMR 13,950.000
- Foundation Waterproofing Membrane75.0% of OMR 4,480.000OMR 3,360.000
The contract price does not change. Each stage is still capped at the share it was allotted — this only changes when inside the stage you are paid for it. Material is claimed at 75.0% while it sits on site, and the balance comes through the work when it is built in.
Commercial summary
PR-2026-001·Stage 01 Preliminaries & Site Setup
Submitted 18 Oct 2026 by Salim Al Hinai
Claim against certificate
- Contractor claimedat 100.0% reported
- OMR 26,000.000
- Consultant certified grossat 100.0% verified
- OMR 26,000.000
- Less retention (5%)
- − OMR 1,300.000
- Less previously certified
- − OMR 0.000
- Net certified
- OMR 24,700.000
Certification and approval chain
Contractor submitted
Salim Al Hinai · 18 Oct 2026
Consultant certified
Eng. Yousuf Al Rawahi · IPC-001 · 22 Oct 2026
Client approved
Ahmed Al Balushi · 25 Oct 2026
Payment recorded
OMR 24,700.000 · 29 Oct 2026
Eng. Yousuf Al Rawahi: Stage 01 works verified complete. Certified in full.
No action available to the contractor on this request.
PR-2027-002·Stage 02 Substructure
Submitted 05 Feb 2027 by Salim Al Hinai
Claim against certificate
- Contractor claimedat 91.3% reported
- OMR 123,437.600
- Consultant certified grossat 82.2% verified
- OMR 111,134.400
- Less retention (5%)
- − OMR 5,556.720
- Less previously certified
- − OMR 0.000
- Net certified
- OMR 105,577.680
OMR 12,303.200 not certified. The consultant reduced the claim to the progress actually verified on site.
Certification and approval chain
Contractor submitted
Salim Al Hinai · 05 Feb 2027
Consultant certified
Eng. Yousuf Al Rawahi · IPC-002 · 11 Feb 2027
Client approved
Pending
Payment recorded
Pending
Eng. Yousuf Al Rawahi: Certified at 82.2% against a claim of 91.3%. Foundation tanking to the north face and backfill compaction evidence remain outstanding and are excluded from this certificate.
No action available to the contractor on this request.
Stages not yet claimed
A payment request can only be raised once verified progress meets the stage threshold.
- Stage 03Ground Floor StructureOMR 66,85081.0% verified
- Stage 04First Floor StructureOMR 57,2001.2% verified
- Stage 05Roofing & BlockworkOMR 46,8000.0% verified
- Stage 06MEP First FixOMR 36,4000.0% verified
- Stage 07Waterproofing & PlasteringOMR 31,2000.0% verified
- Stage 08Tiling, Doors & WindowsOMR 41,6000.0% verified
- Stage 09MEP Second Fix & PaintingOMR 36,4000.0% verified
- Stage 10External WorksOMR 26,0000.0% verified
- Stage 11Testing, Commissioning & HandoverOMR 16,3500.0% verified
Prototype note — No money moves. Payment execution in the real platform runs through the existing contractor-service payment providers and the Finance service; this prototype records a payment against a certificate and stops there. Retention is accrued but release in moieties is not modelled.