Al-Rahma Housing Contract

Payments

Certified value, retention and the commercial position. eBinaa records payments; it never moves money.

2 requests2 certificatesAwaiting client approval

This month's claim

Verified work and material on site — not the whole stage

OMR 68,537.655 net

OMR 16,285 of reported work is not yet verified. Book the consultant — it carries to next month otherwise.

StageVerifiedAlready certifiedEarnedClaim
Ground Floor Structure81.0%OMR 0.000OMR 54,148.500OMR 54,148.500
First Floor Structure1.2%OMR 0.000OMR 686.400OMR 686.400

Material on site, not yet built in

  • Ready-Mix Concrete C40/2075.0% of OMR 18,600.000OMR 13,950.000
  • Foundation Waterproofing Membrane75.0% of OMR 4,480.000OMR 3,360.000
Verified workOMR 54,834.900Material on siteOMR 17,310.000GrossOMR 72,144.900RetentionOMR -3,607.245Net this monthOMR 68,537.655

The contract price does not change. Each stage is still capped at the share it was allotted — this only changes when inside the stage you are paid for it. Material is claimed at 75.0% while it sits on site, and the balance comes through the work when it is built in.

Commercial summary

Contract valueOMR 520,000
Verified work valueOMR 191,969At verified progress
CertifiedOMR 137,134
PaidOMR 24,700
Retention heldOMR 6,8575% of certified
OutstandingOMR 105,578Certified, net, unpaid

PR-2026-001·Stage 01 Preliminaries & Site Setup

Submitted 18 Oct 2026 by Salim Al Hinai

Paid

Claim against certificate

Contractor claimedat 100.0% reported
OMR 26,000.000
Consultant certified grossat 100.0% verified
OMR 26,000.000
Less retention (5%)
− OMR 1,300.000
Less previously certified
− OMR 0.000
Net certified
OMR 24,700.000

Certification and approval chain

  1. Contractor submitted

    Salim Al Hinai · 18 Oct 2026

  2. Consultant certified

    Eng. Yousuf Al Rawahi · IPC-001 · 22 Oct 2026

  3. Client approved

    Ahmed Al Balushi · 25 Oct 2026

  4. Payment recorded

    OMR 24,700.000 · 29 Oct 2026

Eng. Yousuf Al Rawahi: Stage 01 works verified complete. Certified in full.

No action available to the contractor on this request.

PR-2027-002·Stage 02 Substructure

Submitted 05 Feb 2027 by Salim Al Hinai

Consultant Certified

Claim against certificate

Contractor claimedat 91.3% reported
OMR 123,437.600
Consultant certified grossat 82.2% verified
OMR 111,134.400
Less retention (5%)
− OMR 5,556.720
Less previously certified
− OMR 0.000
Net certified
OMR 105,577.680

OMR 12,303.200 not certified. The consultant reduced the claim to the progress actually verified on site.

Certification and approval chain

  1. Contractor submitted

    Salim Al Hinai · 05 Feb 2027

  2. Consultant certified

    Eng. Yousuf Al Rawahi · IPC-002 · 11 Feb 2027

  3. Client approved

    Pending

  4. Payment recorded

    Pending

Eng. Yousuf Al Rawahi: Certified at 82.2% against a claim of 91.3%. Foundation tanking to the north face and backfill compaction evidence remain outstanding and are excluded from this certificate.

No action available to the contractor on this request.

Stages not yet claimed

A payment request can only be raised once verified progress meets the stage threshold.

  • Stage 03Ground Floor StructureOMR 66,85081.0% verified
  • Stage 04First Floor StructureOMR 57,2001.2% verified
  • Stage 05Roofing & BlockworkOMR 46,8000.0% verified
  • Stage 06MEP First FixOMR 36,4000.0% verified
  • Stage 07Waterproofing & PlasteringOMR 31,2000.0% verified
  • Stage 08Tiling, Doors & WindowsOMR 41,6000.0% verified
  • Stage 09MEP Second Fix & PaintingOMR 36,4000.0% verified
  • Stage 10External WorksOMR 26,0000.0% verified
  • Stage 11Testing, Commissioning & HandoverOMR 16,3500.0% verified

Prototype note — No money moves. Payment execution in the real platform runs through the existing contractor-service payment providers and the Finance service; this prototype records a payment against a certificate and stops there. Retention is accrued but release in moieties is not modelled.