Progress
What the contractor claims, what the consultant verified, and the gap between them.
3.1% of claimed progress unverified19 awaiting verification17 behind plan
2 stages are behind on reportingOMR 16,174.500 unclaimed
- Substructureprogramme says 100.0%, you have posted 91.3%OMR 11,762.400
- Ground Floor Structureprogramme says 92.7%, you have posted 86.1%OMR 4,412.100
You cannot be paid for work nobody has been told about. Post the percentage and book the consultant — it goes into this month’s claim rather than next.
Book a site visit
The consultant needs 4 days' notice
19 waiting
- Bulk Excavationdue 22 Oct 20267 days slack
- Excavation for Footingsdue 28 Oct 202613 days slack
- Blinding Concrete to Footingsdue 02 Nov 202618 days slack
- Foundation Formworkdue 12 Nov 202628 days slack
- Foundation Curing & Formwork Strippingdue 21 Nov 202637 days slack
- Waterproofing & Protection to Foundationsdue 26 Nov 202642 days slack
Earliest the consultant can attend is 15 Oct 2026.
Planned43.3%
Contractor reported40.0%
Consultant verified36.9%
Variance-6.4%
Unverified claim3.1%
Prototype note — Site evidence is represented by photo counts and file names — no image storage is wired up. In production, evidence uploads go to the existing File service and are referenced by id, which is why ActivityEvidence carries a file reference rather than a blob.