Al-Rahma Housing Contract

Progress

What the contractor claims, what the consultant verified, and the gap between them.

3.1% of claimed progress unverified19 awaiting verification17 behind plan

2 stages are behind on reportingOMR 16,174.500 unclaimed

  • Substructureprogramme says 100.0%, you have posted 91.3%OMR 11,762.400
  • Ground Floor Structureprogramme says 92.7%, you have posted 86.1%OMR 4,412.100

You cannot be paid for work nobody has been told about. Post the percentage and book the consultant — it goes into this month’s claim rather than next.

Book a site visit

The consultant needs 4 days' notice

19 waiting
  • Bulk Excavationdue 22 Oct 20267 days slack
  • Excavation for Footingsdue 28 Oct 202613 days slack
  • Blinding Concrete to Footingsdue 02 Nov 202618 days slack
  • Foundation Formworkdue 12 Nov 202628 days slack
  • Foundation Curing & Formwork Strippingdue 21 Nov 202637 days slack
  • Waterproofing & Protection to Foundationsdue 26 Nov 202642 days slack

Earliest the consultant can attend is 15 Oct 2026.

Planned43.3%
Contractor reported40.0%
Consultant verified36.9%
Variance-6.4%
Unverified claim3.1%

Prototype note — Site evidence is represented by photo counts and file names — no image storage is wired up. In production, evidence uploads go to the existing File service and are referenced by id, which is why ActivityEvidence carries a file reference rather than a blob.