Al-Rahma Housing Contract
36.9%

Al-Rahma Housing Contract

Active
Planned
43.3%
Reported
40.0%
Checked
36.9%

13 days late
finishing 21 Nov 2027

01
02
03
04
05
06
07
08
09
10
11

Stage 3 of 11·Ground Floor Structure

Cost against the bill

What the work has earned, against what it has cost to get there

All stages within budget

Bill

OMR 520,000.000

Contract stages

Earned

OMR 191,969.300

Verified work

Spent

OMR 101,115.254

Material and labour

Margin so far

OMR 90,854.046

Earning faster than spending

StageBillDoneEarnedSpentPer point
Preliminaries & Site SetupOMR 26,000.000100.0%OMR 26,000.000OMR 12,624.0000.49×
SubstructureOMR 135,200.00082.2%OMR 111,134.400OMR 59,933.7020.54×
Ground Floor StructureOMR 66,850.00081.0%OMR 54,148.500OMR 27,946.5500.52×
First Floor StructureOMR 57,200.0001.2%OMR 686.400OMR 611.0020.89×
Roofing & BlockworkOMR 46,800.0000.0%OMR 0.000OMR 0.000not started
MEP First FixOMR 36,400.0000.0%OMR 0.000OMR 0.000not started
Waterproofing & PlasteringOMR 31,200.0000.0%OMR 0.000OMR 0.000not started
Tiling, Doors & WindowsOMR 41,600.0000.0%OMR 0.000OMR 0.000not started
MEP Second Fix & PaintingOMR 36,400.0000.0%OMR 0.000OMR 0.000not started
External WorksOMR 26,000.0000.0%OMR 0.000OMR 0.000not started
Testing, Commissioning & HandoverOMR 16,350.0000.0%OMR 0.000OMR 0.000not started

Received to date OMR 24,700.000 · OMR 418,884.746 of the bill unspent. Spend is modelled from committed material and the programme in this build; the live version reads your own purchase records, which is why every material wants entering — down to the nails.

All your projects

Where the money is across every job, not just this one

OMR 45,900 overdue

Under contract

OMR 1,315,000

4 projects

Earned

OMR 686,969

Verified across all

Owed to you

OMR 239,569

Earned, not received

Margin

OMR 159,254

1 job losing money

OMR 239,569 of work is done and unpaid across your sites — more than the margin on all of them together. That is the money that does not reach the bank, however profitable the jobs look.

Nizwa Clinic Extension has spent more than it has earned.

Yours alone — no client sees another client’s job. Only the project marked live has figures computed from its own data in this build; the rest are summary records, and inventing three more complete datasets would make every number here a fiction.

What needs you

5 activities on site today

on track
0on track
behind
2behind
blocked
3blocked
  • FF Slab Concrete Pour

    78% of 100%

    Blocked by an open issue

  • FF Column Reinforcement

    10% of 30%

Compaction test certificates — north elevation

Overdue

DR-012: Provide independent compaction test results for the backfill placed to the north elevation.

From
Consultant

Updated structural calculation for first floor slab

UrgentDue 24 Feb 2027

RFI-046: Provide the revised structural calculation supporting the coupler arrangement at gridline 9 following the change issued under S-204 Rev C.

From
Consultant

Waterproofing product certificate

Due 23 Feb 2027

DR-014: Submit the manufacturer product certificate and current test report for the foundation tanking membrane applied to the south and east elevations.

From
Consultant

Get GF Column Concrete Pour checked

Due 24 Feb 2027

Reported done, but only 96% is checked. Nothing gets paid until it is.

Why it’s late: Late structural shop drawing approval

12 key jobs behind · 2 open issues

See what’s holding it up

Recently

All
  • INS-016 requested for staircase core lift 3.21 Feb 2027
  • Comment on STR-430 FF Slab Concrete Pour: honeycombing at column head C4.21 Feb 2027
  • 6 photographs uploaded against STR-440 first floor slab curing.21 Feb 2027
  • Progress reported on STR-440 FF Slab Curing at 55%.21 Feb 2027
  • Aluminium windows — three supplier submissions lodged for technical review.20 Feb 2027
  • RFI-046 raised to the contractor: updated structural calculation for the first floor slab.18 Feb 2027
  • INS-014 approved with comments. Pour to grid 1–6 authorised.17 Feb 2027

Project details

Progress, stages, money and contract

Progress

As at 22 Feb 2027

Planned43.3%
Contractor reported40.0%
Consultant verified36.9%
Variance-6.4%
Unverified claim3.1%

Measured by contract value: OMR 191,969 of OMR 520,000 of work is confirmed done on site.

Next milestone: Ground Floor Structure Complete·expected 17 Mar 2027

Stages

Payment stages, driven by checked progress

  • Stage 01·Preliminaries & Site Setup

    OMR 26,000 · 5% of contract · 5 activities

    Paid
    100% / 100% / 100%
  • Stage 02·Substructure

    OMR 135,200 · 26% of contract · 15 activities

    Client Approval
    100% / 91% / 82%
  • Stage 03·Ground Floor Structure

    OMR 66,850 · 12.86% of contract · 11 activities

    In Progress
    93% / 86% / 81%
  • Stage 04·First Floor Structure

    OMR 57,200 · 11% of contract · 10 activities

    In Progress
    4% / 2% / 1%
  • Stage 05·Roofing & Blockwork

    OMR 46,800 · 9% of contract · 9 activities

    Not Started
    0% / 0% / 0%
  • Stage 06·MEP First Fix

    OMR 36,400 · 7% of contract · 8 activities

    Not Started
    0% / 0% / 0%
  • Stage 07·Waterproofing & Plastering

    OMR 31,200 · 6% of contract · 6 activities

    Not Started
    0% / 0% / 0%
  • Stage 08·Tiling, Doors & Windows

    OMR 41,600 · 8% of contract · 6 activities

    Not Started
    0% / 0% / 0%
  • Stage 09·MEP Second Fix & Painting

    OMR 36,400 · 7% of contract · 7 activities

    Not Started
    0% / 0% / 0%
  • Stage 10·External Works

    OMR 26,000 · 5% of contract · 5 activities

    Not Started
    0% / 0% / 0%
  • Stage 11·Testing, Commissioning & Handover

    OMR 16,350 · 3.14% of contract · 7 activities

    Not Started
    0% / 0% / 0%

Money

Contract value
OMR 520,000.000
Checked work
OMR 191,969.300
Certified
OMR 137,134.400
Held back
OMR 6,856.720
Paid
OMR 24,700.000
Still owed
OMR 105,577.680

Contract

Contract number
CON-2026-0184
Reference
EB-PRJ-2026-0184
Signed
02 Sep 2026
Start
15 Sep 2026
Duration
420 days
Retention
5%
Defects period
12 months
Ahead / behind
-6.4%

Parties

  • Client

    Ahmed Al Balushi

    Ahmed Al Balushi · Owner / Employer

  • Contractor

    Al Noor Construction LLC

    Salim Al Hinai · Main Contractor

    CR 1148296

  • Consultant

    Modern Engineering Consultancy

    Eng. Yousuf Al Rawahi · Supervising Consultant

    CR 1092447 / OSE-C-2214

Looking for something else? It’s all in Records.