Compaction test certificates — north elevation
OverdueDR-012: Provide independent compaction test results for the backfill placed to the north elevation.
- From
- Consultant
Data date 22 Feb 2027 · Forecast completion 21 Nov 2027
13 days late
finishing 21 Nov 2027
Stage 3 of 11·Ground Floor Structure
What the work has earned, against what it has cost to get there
Bill
OMR 520,000.000
Contract stages
Earned
OMR 191,969.300
Verified work
Spent
OMR 101,115.254
Material and labour
Margin so far
OMR 90,854.046
Earning faster than spending
| Stage | Bill | Done | Earned | Spent | Per point |
|---|---|---|---|---|---|
| Preliminaries & Site Setup | OMR 26,000.000 | 100.0% | OMR 26,000.000 | OMR 12,624.000 | 0.49× |
| Substructure | OMR 135,200.000 | 82.2% | OMR 111,134.400 | OMR 59,933.702 | 0.54× |
| Ground Floor Structure | OMR 66,850.000 | 81.0% | OMR 54,148.500 | OMR 27,946.550 | 0.52× |
| First Floor Structure | OMR 57,200.000 | 1.2% | OMR 686.400 | OMR 611.002 | 0.89× |
| Roofing & Blockwork | OMR 46,800.000 | 0.0% | OMR 0.000 | OMR 0.000 | not started |
| MEP First Fix | OMR 36,400.000 | 0.0% | OMR 0.000 | OMR 0.000 | not started |
| Waterproofing & Plastering | OMR 31,200.000 | 0.0% | OMR 0.000 | OMR 0.000 | not started |
| Tiling, Doors & Windows | OMR 41,600.000 | 0.0% | OMR 0.000 | OMR 0.000 | not started |
| MEP Second Fix & Painting | OMR 36,400.000 | 0.0% | OMR 0.000 | OMR 0.000 | not started |
| External Works | OMR 26,000.000 | 0.0% | OMR 0.000 | OMR 0.000 | not started |
| Testing, Commissioning & Handover | OMR 16,350.000 | 0.0% | OMR 0.000 | OMR 0.000 | not started |
Received to date OMR 24,700.000 · OMR 418,884.746 of the bill unspent. Spend is modelled from committed material and the programme in this build; the live version reads your own purchase records, which is why every material wants entering — down to the nails.
Where the money is across every job, not just this one
Under contract
OMR 1,315,000
4 projects
Earned
OMR 686,969
Verified across all
Owed to you
OMR 239,569
Earned, not received
Margin
OMR 159,254
1 job losing money
OMR 239,569 of work is done and unpaid across your sites — more than the margin on all of them together. That is the money that does not reach the bank, however profitable the jobs look.
Nizwa Clinic Extension has spent more than it has earned.
Yours alone — no client sees another client’s job. Only the project marked live has figures computed from its own data in this build; the rest are summary records, and inventing three more complete datasets would make every number here a fiction.
5 activities on site today
FF Slab Concrete Pour
78% of 100%
Blocked by an open issue
FF Column Reinforcement
10% of 30%
DR-012: Provide independent compaction test results for the backfill placed to the north elevation.
RFI-046: Provide the revised structural calculation supporting the coupler arrangement at gridline 9 following the change issued under S-204 Rev C.
DR-014: Submit the manufacturer product certificate and current test report for the foundation tanking membrane applied to the south and east elevations.
Reported done, but only 96% is checked. Nothing gets paid until it is.
10 need your action · 5 with others
DR-012: Provide independent compaction test results for the backfill placed to the north elevation.
On the critical path and behind today's target.
Should have finished by now, and it is on the critical path.
RFI-046: Provide the revised structural calculation supporting the coupler arrangement at gridline 9 following the change issued under S-204 Rev C.
DR-014: Submit the manufacturer product certificate and current test report for the foundation tanking membrane applied to the south and east elevations.
Reported done, but only 96% is checked. Nothing gets paid until it is.
Reported done, but only 95% is checked. Nothing gets paid until it is.
RFI-047 — no reply yet.
CR-008 — no reply yet.
Waiting for the consultant to review it.
Should have finished by now, and it is on the critical path.
Blocked by: Late structural shop drawing approval
Should have finished by now, and it is on the critical path.
Blocked by: Late structural shop drawing approval
On the critical path and behind today's target.
Blocked by: Late structural shop drawing approval
1 more due later — nothing needed today.
Why it’s late: Late structural shop drawing approval
12 key jobs behind · 2 open issues
See what’s holding it upProgress, stages, money and contract
As at 22 Feb 2027
Measured by contract value: OMR 191,969 of OMR 520,000 of work is confirmed done on site.
Next milestone: Ground Floor Structure Complete·expected 17 Mar 2027
Payment stages, driven by checked progress
Stage 01·Preliminaries & Site Setup
OMR 26,000 · 5% of contract · 5 activities
Stage 02·Substructure
OMR 135,200 · 26% of contract · 15 activities
Stage 03·Ground Floor Structure
OMR 66,850 · 12.86% of contract · 11 activities
Stage 04·First Floor Structure
OMR 57,200 · 11% of contract · 10 activities
Stage 05·Roofing & Blockwork
OMR 46,800 · 9% of contract · 9 activities
Stage 06·MEP First Fix
OMR 36,400 · 7% of contract · 8 activities
Stage 07·Waterproofing & Plastering
OMR 31,200 · 6% of contract · 6 activities
Stage 08·Tiling, Doors & Windows
OMR 41,600 · 8% of contract · 6 activities
Stage 09·MEP Second Fix & Painting
OMR 36,400 · 7% of contract · 7 activities
Stage 10·External Works
OMR 26,000 · 5% of contract · 5 activities
Stage 11·Testing, Commissioning & Handover
OMR 16,350 · 3.14% of contract · 7 activities
Client
Ahmed Al Balushi
Ahmed Al Balushi · Owner / Employer
Contractor
Al Noor Construction LLC
Salim Al Hinai · Main Contractor
CR 1148296
Consultant
Modern Engineering Consultancy
Eng. Yousuf Al Rawahi · Supervising Consultant
CR 1092447 / OSE-C-2214
Looking for something else? It’s all in Records.