ISS-021Late structural shop drawing approval
Raised by Salim Al Hinai (Contractor) · 10 Feb 2027
Shop drawings for the first floor slab reinforcement (S-204) were returned Status C twice, delaying rebar fixing at grid 7–9 and the subsequent pour.
- STR-410FF Slab Reinforcement+5 days
- STR-430FF Slab Concrete Pour+4 days
- STR-440FF Slab Curing+3 days
- Shop Drawing S-204 — Status C (1st issue)
- Shop Drawing S-204 — Status C (2nd issue)
- Shop Drawing S-204 — Approved
- RFI-041 — MEP Sleeve Positions
ISS-019Compaction test certificates not provided for north elevation
Raised by Eng. Yousuf Al Rawahi (Consultant) · 16 Jan 2027
Backfill to the north elevation was placed without independent compaction testing. Verification of SUB-170 is suspended until results are provided.
- SUB-170Backfilling & Compaction to Foundations+3 days
- Backfill Compaction — Rejection Notice
ISS-017Waterproofing membrane delivery delayed at port
Raised by Salim Al Hinai (Contractor) · 20 Dec 2026
Imported tanking membrane held in customs clearance for 11 days, delaying foundation waterproofing and the subsequent backfill sequence.
- SUB-160Waterproofing & Protection to Foundations+7 days
- SUB-170Backfilling & Compaction to Foundations+4 days
- Waterproofing Membrane — Customs Clearance
Resolved 05 Jan 2027
ISS-014Municipality permit issued later than tendered assumption
Raised by Salim Al Hinai (Contractor) · 02 Oct 2026
Building permit issued 9 days after the date assumed at tender. Excavation start reprogrammed under Rev 01.
- PRE-130Building Permit & Municipality Approvals+9 days
- EXC-100Site Clearance & Levelling+9 days
- Municipality Building Permit
Resolved 09 Oct 2026
ISS-022Honeycombing at column head C4
Raised by Eng. Yousuf Al Rawahi (Consultant) · 20 Feb 2027
Surface honeycombing identified at column head C4 during post-pour inspection. Making good required before the affected pour can be certified.
- STR-430FF Slab Concrete Pour+2 days
- Honeycombing at C4 — Method Statement for Making Good
Prototype note — Extension-of-time and variation-order calculation is deliberately not implemented. “Estimated impact” is a human judgement recorded against the activity, not an entitlement. The model carries the links a future EOT engine needs — issue → activities → float → completion — which is what decision D-009 puts in scope.