Al Khoud Residential Villa

Procurement

Work packages let to subcontractors, their payment structures, and the supplier register.

4 packages4 subcontractorsOMR 72,800 let

WP-01MEP First & Second Fix

Falaj MEP Contracting LLC · MEP · 22 Jun 2027 → 17 Oct 2027

OMR 42,000Not started

Scope — 11 activities from the main programme

0% verified
  • MEP-100GF Electrical Conduits & Boxes22 Jun 2027
  • MEP-110FF Electrical Conduits & Boxes08 Jul 2027
  • MEP-120Main DB, Riser & Earthing Provisions24 Jul 2027
  • MEP-200GF Water Supply Pipework30 Jun 2027
  • MEP-210GF Drainage & Waste Pipework08 Jul 2027
  • + 6 more

Package payment plan

  • 10%AdvanceOMR 4,200.000Paid
  • 35%First FixOMR 14,700.000Pending
  • 35%Second FixOMR 14,700.000Pending
  • 15%Testing & CommissioningOMR 6,300.000Pending

Plus 5% retention held against the package.

WP-02Aluminium Windows & Glazing

Al Hail Aluminium Works · Aluminium · 16 Sep 2027 → 29 Sep 2027

OMR 13,800Not started

Scope — 1 activities from the main programme

0% verified
  • DRW-100Aluminium Window & Glazing Installation16 Sep 2027

Package payment plan

  • 30%Advance on orderOMR 4,140.000Pending
  • 40%Delivery to siteOMR 5,520.000Pending
  • 25%Installation completeOMR 3,450.000Pending

Plus 5% retention held against the package.

WP-03Internal Joinery & Doors

Dar Joinery & Interiors · Joinery · 28 Sep 2027 → 21 Oct 2027

OMR 9,400Not started

Scope — 2 activities from the main programme

0% verified
  • DRW-110Internal Door Frames28 Sep 2027
  • DRW-120Door Leaves & Ironmongery08 Oct 2027

Package payment plan

No payment plan agreed yet.

WP-04Waterproofing Packages

Gulf Waterproofing Systems · Waterproofing · 22 Nov 2026 → 08 Aug 2027

OMR 7,600In progress

Scope — 5 activities from the main programme

11% verified
  • SUB-160Waterproofing & Protection to Foundations22 Nov 2026
  • ROF-110Roof Waterproofing Membrane17 May 2027
  • WPF-100Wet Areas Waterproofing — Ground Floor24 Jul 2027
  • WPF-110Wet Areas Waterproofing — First Floor03 Aug 2027
  • WPF-120Waterproofing Flood Test & Sign-off17 Aug 2027

Package payment plan

  • 40%Foundation tankingOMR 3,040.000Due
  • 35%Wet areasOMR 2,660.000Pending
  • 20%Roof membraneOMR 1,520.000Pending

Plus 5% retention held against the package.

Prototype note — Subcontractor payments are a separate domain from client-to-contractor payments and never merge with them — they answer to a different contract between different parties.