Al Khoud Residential Villa

Stages

Contract payment stages, mapped to WBS packages and the activities that constitute them.

11 stagesOMR 245,000 contract value1 awaiting decision

Contract stage → construction stage → activities

Progress is rolled up from verified activity progress; value comes from the contract.

StageNameValueActivitiesProgressPlanned / Reported / VerifiedStatusPayment
Stage 01Preliminaries & Site Setup15 Sep 2026 → 15 Oct 2026OMR 12,2505%5100%/100%/100%PaidPaid
Stage 02Substructure06 Oct 2026 → 19 Dec 2026OMR 63,70026%15100%/91%/82%Client ApprovalAwaiting client approval
Stage 03Ground Floor Structure16 Dec 2026 → 04 Mar 2027OMR 31,50012.86%1193%/86%/81%In ProgressNot eligible
Stage 04First Floor Structure20 Feb 2027 → 09 May 2027OMR 26,95011%104%/2%/1%In ProgressNot eligible
Stage 05Roofing & Blockwork09 May 2027 → 24 Jul 2027OMR 22,0509%90%/0%/0%Not StartedNot eligible
Stage 06MEP First Fix22 Jun 2027 → 26 Aug 2027OMR 17,1507%80%/0%/0%Not StartedNot eligible
Stage 07Waterproofing & Plastering24 Jul 2027 → 22 Sep 2027OMR 14,7006%60%/0%/0%Not StartedNot eligible
Stage 08Tiling, Doors & Windows08 Sep 2027 → 20 Oct 2027OMR 19,6008%60%/0%/0%Not StartedNot eligible
Stage 09MEP Second Fix & Painting26 Sep 2027 → 01 Nov 2027OMR 17,1507%70%/0%/0%Not StartedNot eligible
Stage 10External Works16 Sep 2027 → 20 Oct 2027OMR 12,2505%50%/0%/0%Not StartedNot eligible
Stage 11Testing, Commissioning & Handover24 Oct 2027 → 08 Nov 2027OMR 7,7003.14%70%/0%/0%Not StartedNot eligible
TotalOMR 245,000.00089

Prototype note — Stage value is a fixed contract amount scaled by verified progress. The target model (decision D-010) values work against a priced Schedule of Values / BOQ so that partial quantities, variations and materials-on-site have a home. The domain exposes ContractStage.sovLineIds and StageValuation as the seam for that engine — see docs/v2/planning-controls/DATA_MODEL.md.