Concrete Blockwork 200mm
Roofing & Blockwork · 2,850 units
- Approved
- Approved
- Ordered
- 08 Jan 2027
- Arrives
- 04 May 2027
- Needed on site
- 20 May 2027
Part of the order has arrived.
Data date 22 Feb 2027 · Forecast completion 21 Nov 2027
Approval, procurement and delivery for every material, ordered by what is closest to being late.
Roofing & Blockwork · 2,850 units
Part of the order has arrived.
MEP Second Fix & Painting · 6 bathrooms
No supplier submission yet.
Substructure, Ground Floor Structure · 48 tonnes
On site and ready.
Substructure, Ground Floor Structure · 310 m³
On site and ready.
Substructure · 640 m²
On site and ready.
MEP First Fix · Lot
1 submission awaiting technical review.
Tiling, Doors & Windows · 420 m²
With the client to choose — order by 21 Aug 2027.
Tiling, Doors & Windows · 38 units
3 submissions awaiting technical review.