Al-Rahma Housing Contract

Materials

Approval, procurement and delivery for every material, ordered by what is closest to being late.

8 materials2 need you1 at risk on dates

Needs you2

Concrete Blockwork 200mm

Roofing & Blockwork · 2,850 units

Tight
Approved
Approved
Ordered
08 Jan 2027
Arrives
04 May 2027
Needed on site
20 May 2027

Part of the order has arrived.

Sanitary Ware & Fixtures

MEP Second Fix & Painting · 6 bathrooms

On time
Approved
Not submitted
Ordered
Not yet
Arrives if ordered now
No supplier yet
Needed on site
06 Oct 2027

No supplier submission yet.

Everything else6

Reinforcement Steel B500B

Substructure, Ground Floor Structure · 48 tonnes

On site
Approved
Approved
Ordered
30 Sep 2026
Delivered
On site
Needed on site
20 Oct 2026

On site and ready.

Ready-Mix Concrete C40/20

Substructure, Ground Floor Structure · 310 m³

On site
Approved
Approved
Ordered
14 Oct 2026
Delivered
On site
Needed on site
10 Nov 2026

On site and ready.

Foundation Waterproofing Membrane

Substructure · 640 m²

On site
Approved
Approved with comments
Ordered
01 Nov 2026
Delivered
On site
Needed on site
25 Nov 2026

On site and ready.

Electrical Cables & Conduits

MEP First Fix · Lot

On time
Approved
Submitted
Ordered
Not yet
Arrives if ordered now
No supplier yet
Needed on site
22 Jun 2027

1 submission awaiting technical review.

Porcelain Floor Tiles

Tiling, Doors & Windows · 420 m²

On time
Approved
Approved
Ordered
Not yet
Arrives if ordered now
12 Mar 2027
Needed on site
08 Sep 2027

With the client to choose — order by 21 Aug 2027.

Aluminium Windows & Glazing

Tiling, Doors & Windows · 38 units

On time
Approved
Submitted
Ordered
Not yet
Arrives if ordered now
No supplier yet
Needed on site
16 Sep 2027

3 submissions awaiting technical review.