Al-Rahma Housing Contract

Inspections

Requested by the contractor, performed by a named consultant engineer, recorded against specific activities.

INS-014First Floor Slab — Pre-Pour Reinforcement Inspection

Requested by Salim Al Hinai · 14 Feb 2027

CompletedApproved with comments
Consultant
Modern Engineering ConsultancyAttending: Eng. Yousuf Al Rawahi
Location
First floor slab, grid 1–9
Date
Completed 17 Feb 2027
Evidence
18 photos · 1 documents
Related activities (3)
  • STR-410FF Slab Reinforcement
  • STR-420FF Slab MEP Conduits & Sleeves
  • STR-430FF Slab Concrete Pour
Notes
Reinforcement generally in accordance with drawing S-204 Rev C. Cover spacers adequate. Couplers at grid 9 not to specification.
Comments
  • Install couplers at grid 9 per S-204 Rev C before pour to grid 7–9.
  • Re-position two MEP sleeves at grid B6 per RFI-041.
  • Pour to grid 1–6 may proceed.

INS-015First Floor Slab — Post-Pour and Curing Inspection

Requested by Salim Al Hinai · 20 Feb 2027

Scheduled
Consultant
Modern Engineering ConsultancyAttending: Eng. Yousuf Al Rawahi
Location
First floor slab, grid 1–6
Date
Scheduled 26 Feb 2027
Evidence
0 photos
Related activities (2)
  • STR-430FF Slab Concrete Pour
  • STR-440FF Slab Curing
Notes
Post-pour inspection and review of 7-day cube results prior to formwork stripping.
Viewing as contractor

INS-016Ground Floor Shear Wall — Staircase Core Lift 3

Requested by Salim Al Hinai · 21 Feb 2027

Requested
Consultant
Modern Engineering ConsultancyInspector not assigned
Location
Staircase core, ground floor
Date
Not yet scheduled
Evidence
0 photos
Related activities (1)
  • STR-330GF Shear Walls & Staircase Core
Notes
Request to verify remaining 12% of shear wall and staircase core works.
Viewing as contractor

INS-012Foundation Backfill — Compaction Verification

Requested by Salim Al Hinai · 15 Jan 2027

RejectedRejected
Consultant
Modern Engineering ConsultancyAttending: Eng. Yousuf Al Rawahi
Location
North elevation, foundation perimeter
Date
Completed 16 Jan 2027
Evidence
9 photos · 1 documents
Related activities (2)
  • SUB-160Waterproofing & Protection to Foundations
  • SUB-170Backfilling & Compaction to Foundations
Notes
Compaction test certificates not available on site for the north elevation, and tanking to the north face had not been applied. Inspection could not proceed.
Comments
  • Provide compaction test results for the north elevation.
  • Complete tanking and protection board to north face before re-request.

INS-009Ground Slab — Pre-Pour Inspection

Requested by Salim Al Hinai · 10 Dec 2026

CompletedApproved
Consultant
Modern Engineering ConsultancyAttending: Eng. Yousuf Al Rawahi
Location
Ground floor slab, full footprint
Date
Completed 12 Dec 2026
Evidence
22 photos · 1 documents
Related activities (3)
  • SUB-210Ground Slab Hardcore & Blinding
  • SUB-220Ground Slab Reinforcement & Services
  • SUB-230Ground Slab Concrete Pour
Notes
Hardcore, blinding, DPM and reinforcement inspected and accepted. Pour authorised.
Comments
  • Pour authorised for full footprint.